At CoolAir Compressors, we don’t just design custom compressed air systems tailored to your needs—we ensure they are fully operational and optimized for your facility. Once your system has been designed, our team of specialists will handle the installation and commissioning to guarantee a seamless transition from planning to production.
Our expert technicians will manage the entire installation process, ensuring that your compressed air system is up and running on time and meets all operational standards. We offer flexible service options to fit your needs, allowing you to choose the level of involvement that works best for your business. From setup to integration with your existing infrastructure, CoolAir Compressors guarantees a smooth installation process that minimizes downtime and maximizes efficiency.
Once your system is installed, our qualified staff will handle the commissioning phase. This includes configuring your system’s parameters according to your specific operational requirements and conducting a full functionality test. We will ensure that every aspect of the system is working at its peak performance. After commissioning, your team will receive comprehensive training on how to operate and maintain the system, ensuring optimal usage from day one.
Piping Material Features Comparison |
|||
Piping Features | Stainless Steel(Type 304L) | Mild Steel | Blue anodized Aluminum Alloy |
Weight (Dia 6inch, Length 6m) | 127.2 | 169.6 | 29.142 |
Anti-Corrosive | Yes | No | Yes(100%) |
Pressure drop (Dia 2 inch Length= 20m, Airflow=3 cubic metres/Minute, Pressure=10 bar) | 0.25 | 0.4 Bar | 0.1 |
Efficient Energy Use | High | Low-moderate | High( Potential Cost savings of 34%) |
Structural Durability | Very Strong | Very Strong | Strong |
High Thermal Endurance | Yes | Yes | Yes |
Installation Ease | Less Difficult | Difficult | Easy(High Flexibility and Modularity) |
Simple Installation | Approx 6 feet length per hour | Approx 6 feet length per hour | Approx 45 feet Length per hour |
Manpower and Work Hours Needed for 2″ Pipe Over 3000 Feet | Approx 600 man-hours/8 men for 2 weeks | Approx 600 man-hours/8 men for 2 weeks | About 100 man-hours with 8 workers, completed in under 2 days |
Annual Charges for Installation, Commissioning & Operation | Approx 3000 dollars | Approx 7820 dollars | Approx 1300 dollars |
Installation Cost Breakdown: Material % / Labor % | 30% / 70% | 25% / 75% | 80% / 20% |
Texture of Surface | 0.03 | 0.05 | 0.001 |
Required Specialized Tools: Welder, Threader, Groove Cutter | Yes | Yes | No |
Quality of Air | High — When needed, these pipe systems comply with ISO 8573-1:2010 air quality standards | Low( Not according to !SO 8573-2010 air quality standards) | High — These pipe systems support compliance with ISO 8573-1:2010 air quality standards when required. |
Cost Rate per Meter | Almost 2 less than Aluminum | 3 Times less than Aluminum | 163.64 Dollars |
Service Life Depends on Environment, Pipe Design, and Grade | 30 years | 40 years | 20 years |
Upfront Installation Cost | Material : 30% Labor:70% | Material : 25% Labor:75% | Material : 80% Labor:20% |
Care and Maintenance | Difficult — Rust buildup under pipes and fittings can reach machinery, requiring weekly preventive maintenance. | Difficult (Accumulation of rust under pipes and fittings which travels to machinery may require preventive maintenance every 3-4 days) | Easy — No rust buildup, with preventive maintenance needed every 4 weeks. |